Wednesday, July 14, 2004
6.5.2 Test
We tested our combined hardware move and software upgrade on Monday. We moved a test server from the S/390 running 5.08 to an IBM blade server running 6.5.2. All told, basically three hours and that included walking through the notes.ini. I think moving the production server could actually go quicker already having the notes.ini ready will save some time. We'll find out on Friday. If all goes well then we can get Tech Support started on client upgrades.